Here explains the steps to be followed in generating the Cash account for March, supplementary cash book as well as the supplementary cash account and later the general cash book. Great care may be taken in proceeding with the work. So, please go through thisdocument entirely, before the work on supplementary accounts is taken up
Declaring the working days for March and April
During the month of March, when the Day begin is done for the first time in the sub accounts module, the Supervisor is expected to enter the last working day in the month of March and the first working day in the month of April. For the current year 2013, it will be 30.3.2013(last working day in March 2013) and 01.04.2013(first working day in April 2013). This is taken asthe default value in the application. This may kindly be checked up(use the menu Tools – Supplementary dates working as Supervisor). If there are some other dates, they may be changed to 30.3.2013 and 01.04.2013 respectively, before 30th March.